DP World achieves a major milestone by completing dredging works at Ndiaye Port in Senegal
Ahead of Schedule: Major Progress at Ndiaye Port
DP World has achieved a significant milestone in the development of Ndiaye Port, having completed major dredging works 13 months ahead of schedule, at a pivotal station that paves the way for the development of one of Senegal’s most prominent future deep-water ports.
Currently, more than 1,000 people are working directly on the project as construction activities accelerate.
The early completion of the main dredging works represents an important milestone in the project's implementation, as it allows for the start of construction of marine berths and other vital water works ahead of schedule, thus boosting the momentum of the work and supporting the completion of the port in 2028 according to the targeted timetable.
Strengthening Senegal's Role in Global Trade
Once operational, the Ndiaye port will play a pivotal role as Senegal’s main deep-water container gateway, contributing to increased efficiency in international trade, greater port capacity, and consolidating Senegal’s position as a regional logistics hub serving West Africa.
The works included dredging a 5-kilometer-long shipping lane, a ship turning basin, and a mooring channel to accommodate the world's largest container ships. The work was carried out using two of the world's largest vacuum dredgers, underscoring the scale and technical complexity of the project.
Over 95% of the material removed consisted of solid rock, including formations with a compressive strength exceeding 100 megapascals. This reflects the scale of the engineering challenges posed by the development work, as this level of rigidity far surpasses what is typically encountered in major port development projects. Despite these challenging geological conditions, the work was completed without resorting to blasting, minimizing environmental impact and allowing construction to proceed safely.
Driving Long-Term Economic Growth
In this context, Mohammed Akouji, CEO and Managing Director of DP World Africa, said: “The completion of the main dredging works 13 months ahead of schedule marks a significant milestone in the development of Ndiaye Port. It reflects the global expertise, unwavering commitment, and close collaboration of all partners who contributed to delivering this achievement to the highest safety standards. This progress gives us significant momentum to move forward with the next phase of construction, paving the way for the project’s completion in 2028. It also embodies our long-term commitment to Senegal and underscores our confidence in Africa’s growing potential as a key hub in global supply chains. As the largest single private investment in Senegal’s history, valued at US$1.2 billion, this project will play a pivotal role in delivering sustainable economic value by boosting trade, creating jobs, developing connectivity, and enabling long-term economic growth and development opportunities in the region.”
Clarence Rodriguez, CEO of DP World Dakar, said: “This achievement marks a pivotal milestone in our journey to develop world-class infrastructure that will support economic growth and strengthen Senegal’s position as a leading trade and logistics hub in West Africa. The Ndiaye port will play a central role in enhancing the country’s competitiveness, opening new horizons for local businesses, and stimulating sustainable job creation and skills development, supporting approximately 2.3 million trade-related jobs and improving access to essential goods and services for more than 7.8 million people. We are proud of our partnership with the Government of Senegal and all our local partners in implementing this strategic project, which will deliver sustainable economic value to local communities and support Senegal’s development and prosperity.”
Construction work is currently focused on the next phase of water and civil works as the project progresses towards completion in 2028.
Since DP World took over the operational management of the Port of Dakar in 2008, it has invested approximately US$340 million to modernize the terminal and expand its infrastructure, which has enhanced the port's capacity and operational efficiency, thus supporting its position as a major trade gateway in West Africa.
Container handling has seen remarkable growth, rising from 265,000 TEUs (twenty-foot equivalent units) in 2008 to 850,000 TEUs in 2025, in parallel with reducing ship waiting times from 35 hours to almost zero, which has contributed to enhancing operational efficiency and accelerating trade.
Today, the port ranks first in sub-Saharan Africa in terms of efficiency, according to the World Bank's "Global Container Terminal Performance Index".
As the Port of Dakar nears its maximum capacity, DP World, in partnership with the Senegalese government, launched the Ndiaye Port project. This state-of-the-art deep-water gateway represents the next generation of maritime infrastructure in the country, enhancing its ability to accommodate the growing volume of international trade. Located approximately 50 kilometers from Dakar, the new port will allow for future capacity expansion while ensuring more efficient inland logistics services.
Project overview
Originally scheduled for completion in September 2027, dredging work will now conclude in August 2026 thanks to an early start to operations in December 2024, allowing vital engineering work to begin well ahead of schedule.
Juan Carlos Sahadala, the group's head of planning and projects, said: "The core dredging works are one of the most technically complex phases in port development, and completing them ahead of schedule demonstrates the precision of the planning, the efficiency of the execution, and the strength of the collaboration between all parties.
This achievement gives us great momentum to accelerate the implementation of the marine and engineering works, supporting the readiness of the Ndayan port to commence its operations in 2028."
The program was able to develop a 5-kilometer-long navigation channel and deepen it to 20 meters, in addition to creating a turning basin with a diameter of 600 meters and a mooring channel with a length of 875 meters, which enhances the port’s ability to receive two giant Triple E container ships at the same time.
Although more than 95% of the dredged material was rocky, the dredging work was completed without the need to use explosives, thanks to the use of advanced cutter suction dredger technologies, reflecting operational efficiency and a commitment to the highest standards of safety and sustainability.
The project also continued its commitment to the highest environmental and social standards through continuous monitoring and effective communication with various stakeholders, and currently provides employment opportunities for 1,043 employees at the project site.